Structural faults found in Priest River’s Merritt Bridge

By Soncirey Mitchell
Reader Staff

The Bonner County Board of Commissioners declared an emergency loss of access for Merritt Bridge in Priest River on Aug. 11, following the discovery of “a significant infrastructure failure” in two of its pilings. Weight restrictions are in place, and it is unknown whether the bridge, which extends Wisconsin Street across the Pend Oreille River from Priest River to Dufort Road, will shut down during repairs.

The newly cataloged damage may have been caused by construction or manufacturing defects, or “it may have been impacted,” according to Bonner County Road and Bridge Director Jason Topp.

“Two support pilings are compromised. One is completely sheared through; the other has some cracks in it,” said Topp at the Aug. 11 BOCC meeting. “The failure will necessitate either a significant reduction in access or closure of the Wisconsin Street Merritt bridge.”

The Merritt Bridge in Priest River in winter. Photo by Cheri Berger Guinn

The Idaho Transportation Department enlists a dive team to conduct inspections on the underwater pilings every five years, in addition to Bonner County’s above-water inspections every other year. Engineers previously identified a cracked pile, which they drilled into and filled with additional concrete to prevent the cracks from spreading. Road and Bridge received a 2023 federal-aid bridge grant to coat the pilings in an epoxy seal wrap and apply an epoxy driving surface treatment to fix the issue; however, this was before the discovery of the shorn pile. Broader bridge renovations are still in the design phase, with construction scheduled for 2027, but the county will move forward with immediate repairs to the shorn pile.

Following ITD’s instructions, Road and Bridge has instituted a weight restriction of 105,500 lbs per vehicle and is conducting weekly inspections to monitor the bridge’s deterioration until the necessary materials arrive for the repairs, approximately two weeks from Aug. 11. Workers will then dig approximately four feet below the river bed to install and weld a jacket around the base before filling it with “an aggregate or concrete.”

Engineers from Boise-based Marine Solutions are currently assessing the bridge and will determine the need for future restrictions or closure in the coming days. Repairs will take an estimated two weeks.

For future updates, visit bonnercountyid.gov/departments/roadbridge/current-news.

Want to support independent local journalism?

The Sandpoint Reader is our town's local, independent weekly newspaper. "Independent" means that the Reader is locally owned and operated by people who were born and raised in Sandpoint. The Reader is owned by Publisher Ben Olson, Editor-in-Chief Zach Hagadone and Senior Writer Soncirey Mitchell. Sandpoint Reader LLC is a completely independent business unit; no big newspaper group or corporate conglomerate or billionaire owner dictates our editorial policy. And we want the news, opinion and lifestyle stories we report to be freely available to all interested readers - so unlike many other newspapers and media websites, we have NO PAYWALL on our website. The Reader relies wholly on the support of our valued advertisers, as well as readers who voluntarily contribute. Want to ensure that local, independent journalism survives in our town? You can help support the Reader for as little as $1.